The landfill gas power generation project of Luoyang Panlongzhong domestic waste landfill sites, with installed capacity of four 500KW units, was successfully connected to the grid for power generation in January 2009. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on June 11, 2008 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on July 28, 2009, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Luoyang Zhangluoping domestic waste landfill sites, with installed capacity of two 500KW generator units, was successfully connected to the grid for power generation in January 2011. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on February 15, 2011 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on August 24, 2012, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Jiyuan municipal waste landfill sites, with installed capacity of two 500KW generator units, was successfully connected to the grid for power generation in March 2010. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on July 13, 2010 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on April 12, 2012, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Jiaozuo Zhouliu domestic waste landfill sites, with installed capacity of three 500KW generator units, was successfully connected to the grid for power generation in March 2011. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on November 30, 2011 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on February 8, 2012, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Xinxiang municipal waste landfill sites, with installed capacity of four 500KW units, was successfully connected to the grid for power generation in February 2013.
+ DetailsThe landfill gas power generation project of Shangqiu municipal waste landfill sites, with installed capacity of four 500KW generator units, was successfully connected to the grid for power generation in December 2012. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on March 28, 2012 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on July 30, 2012, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Anyang Tanggou domestic waste landfill sites, with installed capacity of four 500KW generator units, was successfully connected to the grid for power generation in May 2011. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on November 25, 2011 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on February 8, 2012, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Hebi municipal domestic waste landfill sites, with installed capacity of two 500KW generator units, was successfully connected to the grid for power generation in May 2013.
+ DetailsThe landfill gas power generation project of Luohe municipal waste landfill sites was connected to power grid successfully for power generation in June 2010. Since then, it has been able to transport about 20 million kilowatt hours of "green power" to state grid every year to address the household power utilization of about 100 thousand residents, relieving the stress in local power supply. The project obtained the clean development mechanism project approval issued by National Development and Reform Commission on July 13, 2010 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on October 7, 2011, the project crediting period is 10 years. In recent years, the state has vigorously promoted and supported green power projects, the waste landfill gas power generation can make rational use of landfill gas resources to effectively reduce the greenhouse effects of landfill gas on atmosphere and the pollution of ambient environment caused by waste landfill, thus to promote the energy conservation and emission reduction.
+ DetailsThe landfill gas power generation project of Pingdingshan municipal waste landfill sites, with installed capacity of three 500KW generator units, was successfully connected to the grid for power generation in September 2013.
+ DetailsThe landfill gas power generation project of Nanyang municipal waste landfill sites, with installed capacity of three 500KW generator units, was successfully connected to the grid for power generation in January 2009. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on June 11, 2008 and was registered successfully under the United Nations Framework Convention on Climate Change (UNFCCC) on January 20, 2011, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Xinyang municipal waste landfill sites, with installed capacity of three 500KW generator units, was successfully connected to the grid for power generation in December 2010. This project obtained the clean development mechanism project approval issued by National Development and Reform Commission on February 15, 2011 and was registered successfully as voluntary emission reductionon project under the gold standard on January 3, 2013, the project crediting period is 10 years.
+ DetailsThe landfill gas power generation project of Zhumadian municipal waste landfill sites, with installed capacity of two 1000KW generator units, was successfully connected to the grid for power generation in January 2014.
+ DetailsThe landfill gas power generation project of Huixian waste landfill sites, with installed capacity of two 500KW generator units, was successfully connected to the grid for power generation in January 2011.
+ DetailsThe landfill gas power generation project of Shenqiu waste landfill sites, with installed capacity of two 500KW generator units, was successfully connected to the grid for power generation in December 2014.
+ DetailsThe landfill gas power generation project of Xiangcheng waste landfill sites, with installed capacity of two 500KW generator units, was successfully connected to the grid for power generation in November 2011.
+ DetailsThe landfill gas project of Zhenping waste landfill sites, with 4*500kw installed capacity, is expected to be connected to the grid for power generation in March 2015.
+ DetailsThe landfill gas project of Ruzhou waste landfill sites, with 4*500kw installed capacity, is expected to be connected to the grid for power generation in March 2015.
+ DetailsPuyang landfill gas power generation projects signed in March 2016, in January 2017 formally connected to the grid, the installed capacity of 2000 kw.
+ DetailsThe waste landfill gas power project in tanghe city, henan province was successfully connected to the grid in December 2017.
+ DetailsThe landfill gas generation project in dengzhou city, henan province, signed in July 2017, is currently under construction and plans to be connected in the first half of 2018.
+ DetailsHenan zhumadian shangcai landfill gas generation project, signed in November 2017, planned to connect the grid in July 2018.
+ Details河南省唐河市垃圾填埋气发电项目,2017年12月成功并网发电。
+ 查看详细南阳邓州垃圾填埋气发电项目,2018年12月并网发电,目前装机0.5兆瓦
+ 查看详细驻马店上蔡垃圾填埋气发电项目,2019年1月并网发电,一期装机1兆瓦
+ 查看详细信阳息县填埋气发电项目2018年11月签约,目前一期项目在建,装机1兆瓦
+ 查看详细驻马店西平填埋气发电项目2018年签约,2019年2月份并网发电,装机1兆瓦
+ 查看详细平顶山鲁山项目2018年7月签约,目前一期项目在建,装机1兆瓦。
+ 查看详细蚌埠市垃圾填埋场填埋气发电项目装机容量为2台1000KW机组,于2014年1月成功并网发电。该项目的实施改善当地居民的居住环境,消除了垃圾填埋场的安全隐患,是目前国际上处理利用生活垃圾的一种主流有效途径。
+ 查看详细宿州市垃圾填埋气发电项目于2014年5月从英国辛迪克公司并购完成,装机容量2000KW。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境,而且消除了垃圾填埋场的安全隐患,还可以节能减排使垃圾资源化,它既符合国家产业政策,又能产生较好的经济效益和良好的社会效益,是目前国际上处理利用生活垃圾的一种主流有效途径。
+ 查看详细肥西垃圾填埋场填埋气项目,装机容量500kw, 2017年并网发电
+ 查看详细宁国垃圾填埋场填埋气项目装机容量4*500kw,预计于15年4月并网发电。
+ 查看详细安徽省马鞍山垃圾填埋场填埋气项目装机容量4*500kw,已在2015年7月成功并网发电。
+ 查看详细安徽省广德垃圾填埋场填埋气发电项目装机容量1000kw,已于2016年成功并网发电。
+ 查看详细安徽省宣城市垃圾填埋气发电项目于2016年8月成功签约,2017年3月成功并网发电。
+ 查看详细安徽省蒙城垃圾填埋气发电项目,2019年1月并网发电,一期装机1兆瓦。
+ 查看详细德化垃圾填埋场填埋气发电项目,目前在建。
+ 查看详细福建泉州垃圾填埋气发电项目2017年12月签约,2018年11月并网发电,一期装机4兆瓦。
福建省福安市垃圾填埋气发电项目,一期装机1兆瓦,2018年并网发电。
福建永春项目2018年11月签约,目前一期项目在建,装机1兆瓦
南京天井洼填埋场填埋气发电项目于2014年9月从深圳市信能环保科技有限公司并购完成,装机容量为2700KW机组。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境,
+ 查看详细江苏省新沂市填埋场填埋气发电项目装机容量1000KW,已于2016年成功并网发电。
+ 查看详细天水市垃圾填埋场填埋气发电项目装机容量为2台500KW机组,于2014年1月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境,
+ 查看详细上饶市垃圾填埋场填埋气发电项目装机容量为4台500KW机组,于2013年8月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境,
+ 查看详细潮州市垃圾填埋场填埋气发电项目装机容量为2台1000KW机组,于2013年12月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境,
+ 查看详细保定垃圾填埋气发电项目于2014年9月从深圳市信能环保科技有限公司并购完成,装机容量2000KW。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境
+ 查看详细柳州市垃圾填埋气发电项目于2014年9月从深圳市信能环保科技有限公司并购完成,装机容量4000KW。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境
+ 查看详细桂林垃圾填埋气发电项目于2014年9月从深圳市信能环保科技有限公司并购完成,装机容量2000KW。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境
+ 查看详细邯郸市垃圾填埋气发电项目于2014年9月从深圳市信能环保科技有限公司并购完成, 装机容量2000KW。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善当地居民的居住环境
+ 查看详细渭南市垃圾填埋场填埋气发电项目装机容量为2台500KW发电机组,已在2015年12月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善了当地居民的居住环境,而且消除了垃圾填埋场的安全隐患。
+ 查看详细乐山活垃圾填埋场填埋气发电项目总投资2828万元,装机容量为4台500KW机组,于2014年12月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善了当地居民的居住环境
+ 查看详细榆林垃圾填埋场填埋气发电项目装机容量为2台500KW发电机组,2014年8月成功并网发电。该项目的实施实现了节能减排,使垃圾资源化,它既符合国家产业政策,又能产生较好的经济效益和良好的社会效益。
+ 查看详细西宁活垃圾填埋场填埋气发电项目装机容量为4台500KW机组,于2014年12月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善了当地居民的居住环境,而且消除了垃圾填埋场的安全隐患。
+ 查看详细武威活垃圾填埋场填埋气发电项目装机容量为4台500KW机组,于2014年12月成功并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善了当地居民的居住环境
+ 查看详细老港工业区热电联供项目,鉴于上海市政府转发的市发战改革委等六部门《关于进一步加大力度改进燃煤(重油)锅炉和窑炉清洁能源替代工作的实施意见》,工业局邀请同济大学、上海城投等单位进行了集中供热的方案论证
+ 查看详细临沂填埋场填埋气项目于2014年9月从深圳市信能环保科技有限公司并购完成,,项目装机容量2000KW,于14 年12月并网发电。该项目的实施不仅解决了垃圾填埋气排空造成的温室效应和环境污染,改善了当地居民的居住环境
+ 查看详细哈尔滨填埋场填埋气项目装机容量5000KW,预计于2016 年6月30日并网发电。
+ 查看详细遵义填埋场填埋气项目于2014年9月从深圳市信能环保科技有限公司并购完成,装机容量2000KW
+ 查看详细荣昌垃圾填埋场填埋气项目装机容量4*500kw,预计于15年4月并网发电。
+ 查看详细韶关市垃圾填埋场填埋气项目装机容量4*500kw,预计于15年4 月并网发电。
+ 查看详细揭西垃圾填埋场填埋气项目,装机容量1000kw,预计于2017年7月31日并网发电。
+ 查看详细桂林二期垃圾填埋场填埋气项目装机容量3090kw,已在2016年2月28日成功并网发电。
+ 查看详细沈阳大辛垃圾填埋气发电项目,2015年并网发电,目前装机8兆瓦,2019年完成增容后,装机10兆瓦。
+ 查看详细陕西省咸阳市垃圾填埋气发电项目,装机容量2000KW,2017年成功并网发电。
+ 查看详细四川省广汉市垃圾填埋气发电项目,装机容量1000kw, 预计2017年7月并网发电。
+ 查看详细揭阳垃圾填埋气发电项目,2017年并网发电,目前装机4兆瓦,增容后达6兆瓦。
+ 查看详细山西省临汾市垃圾填埋气发电项目,我司在晋首个项目,一期装机容量1000KW,2018年1月成功并网发电。
+ 查看详细山东省菏泽市垃圾填埋气发电项目,2017年7月签约,2018年并网发电,一期装机2兆瓦。
+ 查看详细辽宁省大石桥市垃圾填埋发电项目,2017年4月签约,目前在建,一期计划装机1兆瓦。
+ 查看详细辽宁省朝阳市垃圾填埋发电项目,2017年7月签约,目前在建,一期计划装机2兆瓦。
+ 查看详细广西百色垃圾填埋气发电项目,2019年1月并网发电,装机1兆瓦。
+ 查看详细甘肃省庆阳市垃圾填埋气发电项目,一期装机1兆瓦,2017年10月成功并网发电。
+ 查看详细青岛项目2018年4月签约,2018年8月并网,装机7兆瓦,计划2019年二期并网成功,装机7兆瓦,总装机可达14兆瓦。